Pitch Weekly / New Times Downtown KCMO Project

This project was a historic building that had caught fire and was restored. Extra care was needed to minimize the hole coring between floors for network access. Each floor has it's own network termination point. The Main Distribution on the 3rd floor and Intermediate Distribution on 1st and 2nd floors. Backbone connection via fiber optics and 50pr CAT3 cable and a lot of series 4000 wiremold raceway on each floor for station terminations. This is a Belden CAT5e cable and Leviton connectivity products installation.


 

1st floor IDF rack

3rd floor MDF ladder rack

3rd floor MDF 110 feed

Raceway series 4000 around room near floor, multiple network locations

CAT5e back of patch panel

100pr and 50pr CAT3 cable feed thru on back of rack mount 110 block

Raceway

Voice stations on rack mount 110 block for each floor

Raceway behind each cubical and desk for each floor

Raceway locations split with electrical